Hi all,
We are in the process of determining whether our existing 30kVA transformer
will support our presently-installed instrumentation in addition to units
that are slated to be installed soon. Has anyone measured the actual amps
pulled by a Delta V/Conflo/GasBench/TCEA combo? Based on the
manual-provided kW rating for the units, we calculate the amps the be
(1) Delta V baking, all peripherals powered up to be ~37A (2) Power to
Delta V without baking and peripherals powered up to be ~24A. Does this
sound ballpark for either the operational or baking state?
Thanks in advance.
Lora L. Wingate
University of Michigan
Department of Geological Sciences
Stable Isotope Laboratory
1100 North University
1013 C.C. Little Building
Ann Arbor, MI 48109-1005