Sue Bushey <[log in to unmask]>
Reply To:
UVM Occupants of 19 Roosevelt Highway <[log in to unmask]>
Date:
Mon, 10 Nov 2008 11:02:12 -0500
Content-Type:
text/plain
Parts/Attachments:
text/plain (82 lines)
FYI......

-------- Original Message --------
Subject: 	[Fwd: 19 Roosevelt Update]
Date: 	Mon, 10 Nov 2008 10:14:55 -0500
From: 	Julie Barrett <[log in to unmask]>
To: 	Susan Rachael Bushey <[log in to unmask]>
CC: 	Gary Deziel <[log in to unmask]>



Sue:

I know Gary is out today so am wondering if you could share this with 
the appropriate parties in Extension.

-------- Original Message --------
Subject: 	19 Roosevelt Update
Date: 	Mon, 10 Nov 2008 08:49:16 -0500
From: 	Jay Morris <[log in to unmask]>
To: 	Diane M. Edson <[log in to unmask]>, Sue Cramer 
<[log in to unmask]>, Ted Child <[log in to unmask]>, 
<[log in to unmask]>, Cindy Corkins <[log in to unmask]>, 
<[log in to unmask]>, <[log in to unmask]>, Gary Deziel 
<[log in to unmask]>, <[log in to unmask]>, Rebecca Haskell 
<[log in to unmask]>
CC: 	Julie Barrett <[log in to unmask]>



For 19 Roosevelt Highway occupants (106 HPC occupants may disregard):

You’ll have a little reprieve today as work is temporarily on hold 
waiting for new ductwork from the fabrication shop. Work should resume 
tomorrow, with more than half of their work day falling outside of your 
work hours. I’ll get more specifics from the job superintendent later 
today.

All existing ductwork has been cleaned. All units are on the roof and 
sitting over their new mounts. The first new unit should be connected 
and running by the end of this week, with the others soon to follow. The 
concrete floors have been cut to allow the new ducts to run from the 
roof to your respective areas. So in layman’s terms, the heavy lifting 
is done!

In the next couple weeks, the lobby upgrades will begin. But the end 
result will be worth the inconvenience! Thanks for your patience!

Please feel free to communicate with us as the process winds down, if 
you have questions or concerns.

Jay Morris


-- 

Julie Barrett
Real Estate Manager

The University of Vermont and State Agricultural College
Campus Planning Services
109 South Prospect Street
Burlington, VT 05405
(802)656-9360
(802)656-8895, fax
[log in to unmask] <mailto:[log in to unmask]>


-- 

Susan Bushey
Assistant to the Associate Dean
University of Vermont Extension State Office
19 Roosevelt Highway, Suite 305
Colchester VT 05446-5933

Voice: 1-802-656-0733
1-866-622-2990
Fax: 1-802-656-8642
Email: [log in to unmask]
www.uvm.edu/extension <http://www.uvm.edu/extension>

ATOM RSS1 RSS2