    we're going to interrupt the Uninterruptible Power Supply to make it
less interruptible..

> The Uninterruptible Power Supply (UPS) work that was scheduled for
> Tuesday, May 21 has been rescheduled for Wednesday, May 22 due to
> a requirement from Liebert that all their technicians be in a training
> class on Tuesday.
>
> Again, while the upgrade to the UPS is taking place, the Waterman Data
> Center will still be operating on Burlington Electric Power and will not
> experience any outage unless there is an interruption in the supply from
> Burlington Electric.
>
> If you have any questions or concerns, feel free to contact me.
>
> --
> Frank Swasey                    | http://www.uvm.edu/~fcs
> Systems Programmer              | Always remember: You are UNIQUE,
> University of Vermont           |    just like everyone else.
>                     === God Bless Us All ===
>